Construction Of The Marine Facilities Of Fochia Marine Base Command

Project Name : Construction Of The Marine Facilities Of Fochia Marine Base Command
Employer : Republic of Turkey Ministry of Defence General Staff
Contract Date : 12 July 2011
Final Completion : 18 March 2011 – Construction continues
Contract Value : 40,932,362 TL
Job Description : 600m pillar quay + 2 ea 100m piled jetty, transformer building, mounding of the harbour reach and mesh reinforced field concrete, enrockment, dredging and manufacturing rubber collision mats.

 